I am playing what-if with MSP - what if we shorten this task, or change this dependancy. I have created several projects, each with different choices. During discussions, I am sure that one of the tasks common to all the projects will change. I would like to redo this correctly such that I have some sort of base project that I can change, and all the different scenarios would update automatically. Is this possible?
[In scenario A I eat my PB&J at noon, while in B I eat it at 6 pm. I would like to change the length of time it takes to make a PB&J in once, and have it modify both schedules.]
Thanks,
ENN
[In scenario A I eat my PB&J at noon, while in B I eat it at 6 pm. I would like to change the length of time it takes to make a PB&J in once, and have it modify both schedules.]
Thanks,
ENN