This is really an irritating little problem. I have a skeleton project plan that is kept for creation of new standard plans. The problem I have with it is that although the project start date is set to March 2014, whenever I open the plan the Gantt chart is positioned at January 2012. I have looked at just about every option that looks relevant but can't get it to open in 2014.
Any suggestions?
Kevin
This is really an irritating little problem. I have a skeleton project plan that is kept for creation of new standard plans. The problem I have with it is that although the project start date is set to March 2014, whenever I open the plan the Gantt chart is positioned at January 2012. I have looked at just about every option that looks relevant but can't get it to open in 2014.