Hi all,
Although I'm certain I've come across this before, the steps I've tried haven't resolved this issue, so before I spiral out of control into a mess of over thinking:
From the user's email to me (just an aside, the email is titled "HELP". Gotta love it):
[blue]"In Inventory Management, Multiple Level Item View, enter part number 74XYZ. It shows 1,000 on order, 525 on hand.
So click on PO to find the due date of the 1,000 on order, and there are no open lines. The last line was received in January from Hxxxxxx.
Now go to Purchase Order, Scheduled Receipts, by Part Number. Enter 74XYZ. It shows 1,000 on PO 24196 due 8/19."[/blue]
Her question is, 'Why is that not showing up in MLIV?' I've checked that reset qty-on-order and allocations have been run, checked for empty fields in the item number set up, checked that the PO was printed after the change order was done ...
We are using Macola Progression 7.7.400. Am I missing something simple?
Any info, THANKS!
Julie B.
Although I'm certain I've come across this before, the steps I've tried haven't resolved this issue, so before I spiral out of control into a mess of over thinking:
From the user's email to me (just an aside, the email is titled "HELP". Gotta love it):
[blue]"In Inventory Management, Multiple Level Item View, enter part number 74XYZ. It shows 1,000 on order, 525 on hand.
So click on PO to find the due date of the 1,000 on order, and there are no open lines. The last line was received in January from Hxxxxxx.
Now go to Purchase Order, Scheduled Receipts, by Part Number. Enter 74XYZ. It shows 1,000 on PO 24196 due 8/19."[/blue]
Her question is, 'Why is that not showing up in MLIV?' I've checked that reset qty-on-order and allocations have been run, checked for empty fields in the item number set up, checked that the PO was printed after the change order was done ...
We are using Macola Progression 7.7.400. Am I missing something simple?
Any info, THANKS!
Julie B.