Networkdays?

Status
Not open for further replies.

sandybam

Technical User
Mar 20, 2001
43
0
0
US
Hi All,

I would like to figure out how to identify a future date using an identified date and adding only work days in Excel. So for instance, today is 7/15 what date would it be 20 work days from now (M-F)?

Thank you for your help.
Sandy
 


Hi

take a look at WORKDAY()

Skip,
[sub]
[glasses] [red]Be advised:[/red]We know Newton's 3 Laws. But did you hear about the [red]FOURTH???[/red]
Only ONE fig per cookie![tongue][/sub]
 
It's

=WORKDAY(TODAY(),20,Bank_Holiday_List)

where you can have a list of holidays to take into account too.

Cheers, Glenn.