Need urgent help aggregating data. Please help! 2

Status
Not open for further replies.

sssb2000

MIS
Joined
Oct 28, 2010
Messages
5
Location
US
Hi,
i have a project file built and am looking to aggregate the hours for each major deliverable. each major deliverable has several tasks underneath it with hours for each resource. I'm looking to get hours for each resource but for each major deliverable....
the only way i know how to do this is to manually sum up all the hours for each resource for each subtask underneath each major deliverable. Is there a much faster way of automatically doing this?
 
See if the following works in your scenario:

Apply the Task usage view. Create a group to group by: outline Nunber and then by Resource Names (assignment type).
 
^ This worked! thank you for the reply!!!
 
Great. Glad you have what you need and thanks for the feedback.
 
Personally, I think answering an "urgent" problem with a solution that works the first time deserves a star, so please have one Julie.

==================================
The trouble with doing something right the first time is that nobody appreciates how difficult it was - Steven Wright


 
Yes, a star from me too Julie. thank you again!
 
Thank you. You can "star" posts by clicking the star "Like this post link".
 
^ yes. sorry, i failed to "confirm" it on the pop-up window. did it again :-)
 