Tek-Tips is the largest IT community on the Internet today!

Members share and learn making Tek-Tips Forums the best source of peer-reviewed technical information on the Internet!

  • Congratulations Mike Lewis on being selected by the Tek-Tips community for having the most helpful posts in the forums last week. Way to Go!

Need urgent help aggregating data. Please help! 2

Status
Not open for further replies.

sssb2000

MIS
Oct 28, 2010
5
US
Hi,
i have a project file built and am looking to aggregate the hours for each major deliverable. each major deliverable has several tasks underneath it with hours for each resource. I'm looking to get hours for each resource but for each major deliverable....
the only way i know how to do this is to manually sum up all the hours for each resource for each subtask underneath each major deliverable. Is there a much faster way of automatically doing this?
 
See if the following works in your scenario:

Apply the Task usage view. Create a group to group by: outline Nunber and then by Resource Names (assignment type).
 
Personally, I think answering an "urgent" problem with a solution that works the first time deserves a star, so please have one Julie.

==================================
The trouble with doing something right the first time is that nobody appreciates how difficult it was - Steven Wright


 
Thank you. You can "star" posts by clicking the star "Like this post link".
 
^ yes. sorry, i failed to "confirm" it on the pop-up window. did it again :)
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor

Back
Top