Can anybody verify if this type of Holiday table works? I am unable to make it work on two definity systems. Is this a limitation? i can't see it on the manual. sample holiday below:
Start End
mm dd hh mm mm dd hh mm
04/04 21:00 04/05 08:00
The holiday only works if we did the following and separate it into two entries:
Start End
mm dd hh mm mm dd hh mm
04/04 21:00 04/04 23:59
04/05 00:00 04/05 08:00
Thanks. I'd be interested to know why it does not allow the first table (04/04-04/05). Any help is appreciated.
Start End
mm dd hh mm mm dd hh mm
04/04 21:00 04/05 08:00
The holiday only works if we did the following and separate it into two entries:
Start End
mm dd hh mm mm dd hh mm
04/04 21:00 04/04 23:59
04/05 00:00 04/05 08:00