Multiple costs per task

Status
Not open for further replies.

brian8655

Programmer
Jun 7, 2005
5
I have a task in a simple project that requires multiple costs.

For example, the task "Scheduling" has hardware costs and software costs.

Is there any way to record this in the single task, "Scheduling", without creating sub-tasks?

Thanks,
Brian
 
In P2003:

View | Resources
Create a resource named Hardware, change the Type to Material and enter the cost.
Create a resource named Software, change the Type to Material and enter the cost.
View | Gantt
Go to the task and assign those two resources to the task.
 
Beautiful. This is the first time using project. I knew it had to be possible, but searching Google yielded no results. Thank you for the help.
 