MST for 2 days task

Status
Not open for further replies.

JPozo

Technical User
Jun 8, 2002
13
PE
Hello Friends,
I am trying to create a MST using a SJ with one task, but I would like that this task could last 2 days.

When I run MSB740 I just can see the task for one day (Start and finish the same day), I need a task with 2 days (Example Start: 20080715 Finish: 20080716), Now I am changing it manually, but it must be automatic.

Thanks in advance.

Javier Pozo
 
Modify the SJ to include an estimate of the time required to do the job, e.g. 48 hrs.
 
Or, create a 2nd task for the 2nd day, and set the Offset to 1 - so it always follows the 1st task by 1 day.
 