Tek-Tips is the largest IT community on the Internet today!

Members share and learn making Tek-Tips Forums the best source of peer-reviewed technical information on the Internet!

  • Congratulations John Tel on being selected by the Tek-Tips community for having the most helpful posts in the forums last week. Way to Go!

MSP 2000 Critical path not showing

Status
Not open for further replies.

davidd31415

Programmer
Jan 25, 2006
154
US
I'm using Project 2000 and am not able to see the critical path of my project when selecting the Tracking Gantt. Does anyone know why this might happen?

This problem started when I broke a project into several smaller projects and then created a consolidated project. I was hoping I could see critical paths for each individual project inserted into the consolidated project by using the "calculate multiple critical paths" option but this doesn't seem to do that. I then started opening the individual projects in hopes that I could see one critical path at a time but none are shown. I've tried using the Gantt Wizard but still no red shows on the chart...

Any ideas would be appreciated!

Thank you,

David
 
I've seen this happen ... somewhere I've actually got the instructions to create the display.

In the past, I "fixed" the display by:

Tools | Options | Calculation-tab and putting a checkmark in "Calculate multiple critical paths".

 
Status
Not open for further replies.

Part and Inventory Search

Sponsor

Back
Top