MS Projects 200 inaccurate summary percent complete

Status
Not open for further replies.

YANKRAY

Technical User
Nov 7, 2003
283
I am using MS Projects 2000.

I have a Project Flow chart with basic start/finish information and three Summary Tasks.

For one of my Summary tasks, the percent complete line shows about 7 days behind schedule even though all the tasks that make up the summary are either on schedule or ahead of schedule.

Any ideas why the low percentage complete?
 