YANKRAY
Technical User
- Nov 7, 2003
- 283
I am using MS Projects 2000.
I have a Project Flow chart with basic start/finish information and three Summary Tasks.
For one of my Summary tasks, the percent complete line shows about 7 days behind schedule even though all the tasks that make up the summary are either on schedule or ahead of schedule.
Any ideas why the low percentage complete?
I have a Project Flow chart with basic start/finish information and three Summary Tasks.
For one of my Summary tasks, the percent complete line shows about 7 days behind schedule even though all the tasks that make up the summary are either on schedule or ahead of schedule.
Any ideas why the low percentage complete?