MS Project fails to update date fields.
This is with an existing projects with there are no fixed dates.
I've noticed this in 2 circumstances:
First when entering %cent complete. This does not change any dates.
Second when changing the date of a task that was due prior to "now" but which is being rescheduled for a few days from "now". Again in some unknown circumstances, Project does not reschedule dependent future tasks.
We've checked dependencies and there are no other fixed dates.
Has anyone seen these problems and does anyone know of a solution.
This is with an existing projects with there are no fixed dates.
I've noticed this in 2 circumstances:
First when entering %cent complete. This does not change any dates.
Second when changing the date of a task that was due prior to "now" but which is being rescheduled for a few days from "now". Again in some unknown circumstances, Project does not reschedule dependent future tasks.
We've checked dependencies and there are no other fixed dates.
Has anyone seen these problems and does anyone know of a solution.