Hi all, I am trying to limit the number of working hours to 6hours a day. In change working times, I have changed the default hours per day and week to 6hrs and 30hrs respectively. But when I allocate durations to tasks, it still counts it for 8hr days and I can't seem to change it?
I want to enter 4 days (6hours per day = 24hours) but when I enter 4 days, MS project calculates start and end date to be 3 days (8 hours per day = 24 hours). Any idea how to fix this please??
I want to enter 4 days (6hours per day = 24hours) but when I enter 4 days, MS project calculates start and end date to be 3 days (8 hours per day = 24 hours). Any idea how to fix this please??