Does anyone know in which table the reschedule date displayed in MD04 is held.

I know the structure is MDEZ and the field is UMDAT but need the table for use in a Query.
 
I believe the data you are looking for is in the MRP tables MDTB and MDKP. I use these tabels currently to create a batch file for rescheduling production orders.
 
Thanks for your reply mbar65.
In MDKP I can see the link from Material to an MRP Table reference but our MDTB table only contains 7 records - they look like junk with Planned Dates of 0 or 1992.
 