Hello, I have what I think is a sticky MRP issue. I have an item that is a component of a BOM. We are now going to acquire this item, stock and ship as a FG item as well as continue to include as a component of the BOM. There is a kicker… When this item is in FG, the item is acquired as a consigned item with no standard cost, while the component item will continued to be purchased, owned and valued in inventory with a standard cost. These items are ordered on separate PO’s from the same vendor and are the same part number. These items will be carried in two different Macola Locations and NEVER co-mingled.
Question: Is there any way to set up Macola so that the Computer Planned Order reflects the requirements specific to both the purchased component item and consigned FG item?
Any help greatly appreciated!