Feb 20, 2006 #1 obede Technical User Jan 26, 2006 8 BR Hi dear I configured the working time to 8 hrs/day and I created tasks with less than 8 hrs. Why doesn't the milestone duration match the sum of taks? Thank you very much Obede Brazil
Hi dear I configured the working time to 8 hrs/day and I created tasks with less than 8 hrs. Why doesn't the milestone duration match the sum of taks? Thank you very much Obede Brazil
Feb 20, 2006 #2 PDQBach IS-IT--Management Sep 26, 2003 1,523 US By definition, a milestone is 0work and 0duration. Upvote 0 Downvote
Feb 21, 2006 Thread starter #3 obede Technical User Jan 26, 2006 8 BR The milestone shows the sum of tasks. Upvote 0 Downvote
Feb 21, 2006 #4 PDQBach IS-IT--Management Sep 26, 2003 1,523 US No. A summary task shows the sum of tasks; a milestone is still a task with 0work and 0duration. Upvote 0 Downvote