Hi dear

I configured the working time to 8 hrs/day and I created tasks with less than 8 hrs.
Why doesn't the milestone duration match the sum of taks?

Thank you very much

Obede
Brazil
 
By definition, a milestone is 0work and 0duration.
 
The milestone shows the sum of tasks.
 
No. A summary task shows the sum of tasks; a milestone is still a task with 0work and 0duration.
 