Tek-Tips is the largest IT community on the Internet today!

Members share and learn making Tek-Tips Forums the best source of peer-reviewed technical information on the Internet!

  • Congratulations strongm on being selected by the Tek-Tips community for having the most helpful posts in the forums last week. Way to Go!

Maintenance activities - How to control

Status
Not open for further replies.

FlavioMT

MIS
Jan 7, 2002
7
BR
Anybody have tips about use Microsoft project to control activities that aren’t be in a normal project structure (maintenance tasks for instance)?

Regards,
Flávio Teixeira
 
You can use Project to handle maintenance tasks a couple of ways. Using the "Insert" menu you can enter recurring tasks, or just schedule a series of maintenance tasks. Just put in the appropriate resource(s) and predecessor(s). No real magic to it.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor

Back
Top