Hi,
Now here's a challenge...
Where I am, resource availability is scattered, ie. people are allocated to projects on and off for a few days at a time over the duration of the project. Entering this into the resource availability dialogue manually every time bookings are updated is error prone and time consuming.
I can get my bookings massaged into this format in Excel:
<ressource name> <from date> <to date>
<ressource name> <from date> <to date>
...
With as many lines per ressouce as necessary (one per period). Now, if I import this into project 2007, i get one ressource item per line in excel, i.e. a lot of duplicates. Of course I haven't got 10 copies of the same person, I have the same person 10 times, ie. 10 pairs of "available from" and "available to" on the same person. The from and to dates are not imported at all.
Any ideas on how to get this to work? I have been using the resource name as the merge key, but no luck so far.
Thanks a lot,
Jens
Now here's a challenge...
Where I am, resource availability is scattered, ie. people are allocated to projects on and off for a few days at a time over the duration of the project. Entering this into the resource availability dialogue manually every time bookings are updated is error prone and time consuming.
I can get my bookings massaged into this format in Excel:
<ressource name> <from date> <to date>
<ressource name> <from date> <to date>
...
With as many lines per ressouce as necessary (one per period). Now, if I import this into project 2007, i get one ressource item per line in excel, i.e. a lot of duplicates. Of course I haven't got 10 copies of the same person, I have the same person 10 times, ie. 10 pairs of "available from" and "available to" on the same person. The from and to dates are not imported at all.
Any ideas on how to get this to work? I have been using the resource name as the merge key, but no luck so far.
Thanks a lot,
Jens