Throbinski
Technical User
Hi there,
I'm having a problem trying to import data from MS Excel into MS Project.
I have an Excel spreadsheet with each row is basically an assignment (contains activity name and end date (task info) and Owner(resource info)) - I'm therefore trying to set up an assignment map that maps the following information (Excel field name -> Project field name):
Activty -> Task Name
Date -> Finish
Owner -> Resource Name
Activity and Owner are mapping fine. However, the date will not correctly map to the finish field - Project seems just to ignore it and enter the current date as both start and finish dates.
I can map Date -> Finish fine if using a Task mapping, but of course, then I can't import the Owner information. I assume its something particular about Assignment Mappings, but I don't know what.
Does anyone have any ideas what might be causing this and how to fix it?
Thanks very much for any help
I'm having a problem trying to import data from MS Excel into MS Project.
I have an Excel spreadsheet with each row is basically an assignment (contains activity name and end date (task info) and Owner(resource info)) - I'm therefore trying to set up an assignment map that maps the following information (Excel field name -> Project field name):
Activty -> Task Name
Date -> Finish
Owner -> Resource Name
Activity and Owner are mapping fine. However, the date will not correctly map to the finish field - Project seems just to ignore it and enter the current date as both start and finish dates.
I can map Date -> Finish fine if using a Task mapping, but of course, then I can't import the Owner information. I assume its something particular about Assignment Mappings, but I don't know what.
Does anyone have any ideas what might be causing this and how to fix it?
Thanks very much for any help