hi,I need your help!
my situation: I updated my project with actual work figures. the baseline work of one task was 15 hours. by mistake i added 15 days. my trackin gantt of course reacted this and channged the duration etc.
then i updated the actual work - now with correct figures: 15 hours - BUT the tracking gantt remained as it was after the wrong update (15days).
what if i notices my mistake, so that i cannot get back with the undo's. is there any way to 'recalculate' the plan?
my situation: I updated my project with actual work figures. the baseline work of one task was 15 hours. by mistake i added 15 days. my trackin gantt of course reacted this and channged the duration etc.
then i updated the actual work - now with correct figures: 15 hours - BUT the tracking gantt remained as it was after the wrong update (15days).
what if i notices my mistake, so that i cannot get back with the undo's. is there any way to 'recalculate' the plan?