Masquerouge
IS-IT--Management
Example:
one of my developers has to schedule three 2-hour meeting with a client, before end of October.
What I would like to see in project:
Duration=6 hours
start=1-aug
finish= 31-Oct
I've been playing with resource units (%age) and task type (fixed duration) but I must have missed the proper combination because I did not manage to get a satisfactory output: either the duration would jump very high (600 hours) if I lowered resource units to 1%, or the start date would move to 31-Oct, or the finish date would move to 1-aug.
Is there a way to properly display what I want?
Thanks!
one of my developers has to schedule three 2-hour meeting with a client, before end of October.
What I would like to see in project:
Duration=6 hours
start=1-aug
finish= 31-Oct
I've been playing with resource units (%age) and task type (fixed duration) but I must have missed the proper combination because I did not manage to get a satisfactory output: either the duration would jump very high (600 hours) if I lowered resource units to 1%, or the start date would move to 31-Oct, or the finish date would move to 1-aug.
Is there a way to properly display what I want?
Thanks!