Hi:
I am using MS Project 2007 Professional (stand-alone) and have inserted several schedules into a master schedule with the link checkbox checked. I deleted one schedule from this group, but the master schedule still thinks it is there and is displaying tasks and work from this deleted sub-schedule under task and resource usage views. How can I get rid of this "phantom schedule", so that the master starts displaying tasks and calculating correctly again?
Thanks,
David
I am using MS Project 2007 Professional (stand-alone) and have inserted several schedules into a master schedule with the link checkbox checked. I deleted one schedule from this group, but the master schedule still thinks it is there and is displaying tasks and work from this deleted sub-schedule under task and resource usage views. How can I get rid of this "phantom schedule", so that the master starts displaying tasks and calculating correctly again?