MS project doesn't have a field to compute the planned percentage of completion! MS Project has BCWS which is similar to my request, but it will not compute the planned percentage of completion for those tasks that has no cost, no resources assigned. My request is very simple; if I have many tasks in my project (some with assigned cost and others with no cost), at any time I want to know (on the task level and on the project level) what is the planned percentage of completion regardless of the cost.
Example;
If I have a project with the following tasks:
Name Duration Sdate Edate
T1 10 01-01-07 10-01-07
T2 10 11-01-07 21-01-07
T3 20 01-03-07 20-03-07
If I save this baseline,I need a field (planned Percentage completion)to have the following values:
if the status date is:
10-01-07 -----> planned Percentage completion should show 25%
21-01-07 -----> planned Percentage completion should show 50%
28-01-07 -----> planned Percentage completion should show also 50%
15-02-07 -----> planned Percentage completion should show also 50%
28-02-07 -----> planned Percentage completion should show also 50%
20-03-07 -----> planned Percentage completion should show also 100%
Thank you in advance.
Example;
If I have a project with the following tasks:
Name Duration Sdate Edate
T1 10 01-01-07 10-01-07
T2 10 11-01-07 21-01-07
T3 20 01-03-07 20-03-07
If I save this baseline,I need a field (planned Percentage completion)to have the following values:
if the status date is:
10-01-07 -----> planned Percentage completion should show 25%
21-01-07 -----> planned Percentage completion should show 50%
28-01-07 -----> planned Percentage completion should show also 50%
15-02-07 -----> planned Percentage completion should show also 50%
28-02-07 -----> planned Percentage completion should show also 50%
20-03-07 -----> planned Percentage completion should show also 100%
Thank you in advance.