CornishPlanner
Technical User
Hi Everyone, Lets see if I can explain this properly, I am a planning engineer and I am currently looking after a Scheme where we have reduced the programme (removing hidden float) and we have agreed with the client that we will track our Reduced Target date against his Contractual completion date however in order to ensure we show a critical path and to divide the "Safety" up amongst Civils, M&E and Commissioning elements (sub contractors) we need tasks between the Target completion and the Contract completion that we have called "Time Risk Allowance".
What I am trying to do is for the "buffer, or Risk Allowance" tasks to stay where they are (manual update perhaps) so we don't move or show a delay to the Client completion date however when we reschedule the programme if we are showing delay to works before the "Buffer" (Extremely likely as the scheme will complete in 2015) we want it to automatically consume the buffer by showing %complete rather than either just give a warning that the Manually scheduled task may be delayed and have to add progress manually or auto re-scheduling the incomplete buffer to start after the delayed predecessor and therefore needing a -ve lag or similar manual intervention to get the Client date back to where we want it.
I have started to investigate VBA as I think if I am to be telling project to mark a specific task with %complete it might have to be programmed rather than a Formula so I don't mind doing that but I would need guiding through it. Is there anyone who can help. Many thanks Alex
What I am trying to do is for the "buffer, or Risk Allowance" tasks to stay where they are (manual update perhaps) so we don't move or show a delay to the Client completion date however when we reschedule the programme if we are showing delay to works before the "Buffer" (Extremely likely as the scheme will complete in 2015) we want it to automatically consume the buffer by showing %complete rather than either just give a warning that the Manually scheduled task may be delayed and have to add progress manually or auto re-scheduling the incomplete buffer to start after the delayed predecessor and therefore needing a -ve lag or similar manual intervention to get the Client date back to where we want it.
I have started to investigate VBA as I think if I am to be telling project to mark a specific task with %complete it might have to be programmed rather than a Formula so I don't mind doing that but I would need guiding through it. Is there anyone who can help. Many thanks Alex