Tek-Tips is the largest IT community on the Internet today!

Members share and learn making Tek-Tips Forums the best source of peer-reviewed technical information on the Internet!

  • Congratulations Mike Lewis on being selected by the Tek-Tips community for having the most helpful posts in the forums last week. Way to Go!

How can I set the start date?

Status
Not open for further replies.

DavidThi808

Programmer
Sep 27, 2004
3
US
Suddenly my first task (all other tasks are sub-tasks under it) won't let me set the start date. Any idea why that is disabled and how I get it enabled?

thanks - dave
 
I just tried a beta project I'm working on in MSP-07, I tried changing the Constraint Types to "Must Start On" and several others, other than "Start No Earlier Than" and I have no issues. Have you tried changing the Start Date under Project Information? The "Schedule From" I have selected is the default "Project Start Date".
 
You have hidden the "Start" column.

Click on any column header (to select the entire column), press the <Ins> key and select the "Start" column.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor

Back
Top