I have a schedule that is a combination of regular project work and work to be completed during a plant shutdown. During the regular work the working time is a normal 8 hours per day. When the plant shuts down the work schedule changes to 2 10 hour shifts giving a "day" a value of 20 hours. My problem is that my duration field is calculating based on the 8 hrs/day value and during the shutdown it is stretching out a tasks duration based on the 8 hrs. Is there a way to define the two different values? Is there a way to compensate for the difference or do I need 2 seperate schedules?