I would like to send my MS Projects out to team members in order to obtain status updates. Before I send the projects out I would like to run a filter or use a formulat that highlights in "red" the fields that need their status updated.
Below are the date fields and Task Status Guidelines.
Baseline Start, Baseline Finish, Start, Finish, Start 3 (Estimated Start Date), Finish 3 (Estimated Finish Date), Acutal Start, Acutal Finish + the % Complete Field.
Task Status Guidelines
If a task has started but has not finished, the Actual Start Date needs to be updated and the % Complete also needs to be updated.
If a task has started and is now complete the Actual Finish Date needs to be updated and the % Complete also need to be updated to 100 %.
If a task has started and the but the finish date changes add the new finish date to the Estimated Finish date field (Finish 3)and update the % Complete.
If a task is past due according to the Baseline Start and Finish Dates please update the new Estimated Start (Start 3) and Estimated Finish (Finish 3)date fields with the new dates.
Below are the date fields and Task Status Guidelines.
Baseline Start, Baseline Finish, Start, Finish, Start 3 (Estimated Start Date), Finish 3 (Estimated Finish Date), Acutal Start, Acutal Finish + the % Complete Field.
Task Status Guidelines
If a task has started but has not finished, the Actual Start Date needs to be updated and the % Complete also needs to be updated.
If a task has started and is now complete the Actual Finish Date needs to be updated and the % Complete also need to be updated to 100 %.
If a task has started and the but the finish date changes add the new finish date to the Estimated Finish date field (Finish 3)and update the % Complete.
If a task is past due according to the Baseline Start and Finish Dates please update the new Estimated Start (Start 3) and Estimated Finish (Finish 3)date fields with the new dates.