Hi all!! Its me again, lol
I created a bunch of milestones. in the gant view i changed the marker to red and have a project number next to each milestone marker which is now an arrow. Can i change that text color as well for the gant view?

Also, when i switch to the calendar view the diff tasks show...i want to color code those as well but when I change one oclor they all go that same color. Can i have multiple colors appear on the calendar view to represent the diff tasks?

Thanks again in advance!

~Krista~
 
On the Gantt chart: you cannot control the colour of the text.

On the "spreadsheet": Format | Text styles, select Milestones and set up the default text colour for all milestones; or

Select the individual task and set the text colour for it.


On the Calendar display: you cannot control the colour of individual tasks.
 
ok..thats what I ran into but I just wanted to double check with the experts! Thank you!

~Krista~
 