Hi:
I had created a project plan which used custom date fields in a formula for each task (an executive dashboard kind of thing with graphical indicators to show which tasks are started, not yet started, on schedule, over schedule, etc.). It was working just fine until I started adding subtasks and the original task became a summary task.
Now the formulas no longer work in the summary tasks. They continue to work properly in the sub tasks. Why would they have stopped working? They are still looking at the same field for evaluation, but now the field is a summary field. Why doesn't work any more?
I am using Project 2000.
Thanks!
I had created a project plan which used custom date fields in a formula for each task (an executive dashboard kind of thing with graphical indicators to show which tasks are started, not yet started, on schedule, over schedule, etc.). It was working just fine until I started adding subtasks and the original task became a summary task.
Now the formulas no longer work in the summary tasks. They continue to work properly in the sub tasks. Why would they have stopped working? They are still looking at the same field for evaluation, but now the field is a summary field. Why doesn't work any more?
I am using Project 2000.
Thanks!