Hi,
I want to have a column that can show how many days is really delayed while the task is even not finished yet. I try to use a duration1 and use the formula to calculate : Current Date - Baseline Finish Date, but it didn't work. Please help.
On the other hand, I would this figure show 0 if the current date is the same or earlier than the Baseline finish date. And if it is finished, the figure should be showing as nothing or equal to the Finish Variance.
I am not sure if my question is clear enough. I hope there will be solution. Thanks.
I want to have a column that can show how many days is really delayed while the task is even not finished yet. I try to use a duration1 and use the formula to calculate : Current Date - Baseline Finish Date, but it didn't work. Please help.
On the other hand, I would this figure show 0 if the current date is the same or earlier than the Baseline finish date. And if it is finished, the figure should be showing as nothing or equal to the Finish Variance.
I am not sure if my question is clear enough. I hope there will be solution. Thanks.