Tek-Tips is the largest IT community on the Internet today!

Members share and learn making Tek-Tips Forums the best source of peer-reviewed technical information on the Internet!

  • Congratulations Mike Lewis on being selected by the Tek-Tips community for having the most helpful posts in the forums last week. Way to Go!

Equipment won't Increase Work

Status
Not open for further replies.

Andrewlevitt257

Technical User
Apr 10, 2006
1
0
0
US
How do I assign equipment resources to a task without increasing the work that that task takes, while still taking advantage of work resource functions like load levelling and max units, etc.?
 
Levelling levels work so "adding equipment without increasing the work" is somewhat contradictory.

Perhaps you could reply giving some specific numbers that you used, the results that you got and the results you wanted.
 
Could this not be as simple as the equipment needing to be a "material resource" and not a "work" resource? If you add the column "resource type" you should be able to change the equipment to "material" instead of "work". Not sure though.
 
I suspect Adam is absolutely correct on this but just to be sure I asked to see what Andrew was seeing and expecting.
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor

Back
Top