Hi All,
I am new to this board so I hope this question isn't too elementary for some of you seasoned folks.
I'm trying to display milestones of 9 different projects in one file. I did this by creating 9 separate files with tasks and milestones and then one high-level file that has all 9 project files imported. The goal is to have all of the project milestones displayed on each project's highest-level timeline. The problem I'm running into is that if I have many milestones on the same date, I can't seem to display all of the milestones on the timeline because (A) nowhere to fit the text and (B) not all of the milestones roll-up to the high-level for some reason.
Is it possible to display something like this:
Date
4/1/2009
Milestone 1 Name
Milestone 2 Name
Milestone 3 Name
Highest-level: Start--------------*------------------End
Finish Date
Milestone 1 Name
Lower Level: *
Finish Date
Milestone 2 Name
Lower Level: *
Finish Date
Milestone 3 Name
Lower Level: *
Finish Date
I know how to display the Lower Level Milestone Names/Dates, but I can't seem to get the highest-level display. Any suggestions?
Thanks!
I am new to this board so I hope this question isn't too elementary for some of you seasoned folks.
I'm trying to display milestones of 9 different projects in one file. I did this by creating 9 separate files with tasks and milestones and then one high-level file that has all 9 project files imported. The goal is to have all of the project milestones displayed on each project's highest-level timeline. The problem I'm running into is that if I have many milestones on the same date, I can't seem to display all of the milestones on the timeline because (A) nowhere to fit the text and (B) not all of the milestones roll-up to the high-level for some reason.
Is it possible to display something like this:
Date
4/1/2009
Milestone 1 Name
Milestone 2 Name
Milestone 3 Name
Highest-level: Start--------------*------------------End
Finish Date
Milestone 1 Name
Lower Level: *
Finish Date
Milestone 2 Name
Lower Level: *
Finish Date
Milestone 3 Name
Lower Level: *
Finish Date
I know how to display the Lower Level Milestone Names/Dates, but I can't seem to get the highest-level display. Any suggestions?