First of all you guys are great!

I was hoping to create a report just based on what tasks are overdue for all resources instead of just one...possible?
 
Possible? Sure. Oh, even though you didn't ask for it, here's one approach.

Click on Project | Filtered for xxxx | More filters...

Click on the "Task" radio button
Click on the "New" button.

In the popup:
Change the Name to "PDQBach Late Tasks"
Put a check in "Show in menu"

Set up the conditions you want. I chose:
Code:
   Baseline Finish | Does not equal | NA
   And | Finish | Is greater than | [Baseline Finish]
   And | %Work Complete | does not equal | 100

Apply the new filter and you'll see the late tasks.

With only a little more effort, you can modify the canned "Late Tasks/Over budget" report to show the same tasks.
 
I almost did ask but figured someone would tell me...thank you!

~Krista~
 