Creating a Report to Show Work to be Done

Status
Not open for further replies.

BTuffery

Technical User
Jul 1, 2005
18
GB
Can anyone help? I am trying to create a report in project 2002 that shows the number of work hours planned, per resource, per month by task name, until the end of the project. I am not very familar with the report function in project and any suggestions would be very much appreciated.

Thanks
 
View | Reports | Assignments | Who-does-what-when
 
thanks. Do you know if there is a way of showing who does what when by task summary rather than the break down of each sub task? I've played with the filters to no avail.
 
Not without writing some VBA code.

(And, to save you from loads of grief down the road: don't assign resources to summary tasks as a workaround.)
 