matmit
Technical User
- Dec 4, 2006
- 7
I am trying to find a report that will show a matrix or crosstab of the resources down the left of a page, the dates across the top of the page and where a certain column and row meet will be the task that resource is to do on that day.
I am trying my best to have our Foreman agree to throw away the pencil and paper timesheet matrix (which is a simple printed MS Word table that they hand-write, each week, the "MS Project" scheduled work for the coming two weeks) and instead to go with a report from MS Project. Our Forman open the resource pool and scheduled works file in MS Project and then hand-write the information on their printed table. Just too old school for me to continue with!! We may a well just schedule with pencil and paper too (if I cant show them that MS Project can produce a report of exactly what they are hand-writing)
The Resource of Task Usage views and the calendar views are unable to produce the information that our Forman require.
I need more like an excel spreadsheet where Column A = Resources and Row 1 = Dates. Then the cells that align with the resource and the date will show the task for the day, similar to that of a times table situation.
Please help me change their old ways to a better MS Project way.
I have also tried this in a testdrive of P2007 but still can not get the task name to appear, i can only get the work hours to appear.
I am trying my best to have our Foreman agree to throw away the pencil and paper timesheet matrix (which is a simple printed MS Word table that they hand-write, each week, the "MS Project" scheduled work for the coming two weeks) and instead to go with a report from MS Project. Our Forman open the resource pool and scheduled works file in MS Project and then hand-write the information on their printed table. Just too old school for me to continue with!! We may a well just schedule with pencil and paper too (if I cant show them that MS Project can produce a report of exactly what they are hand-writing)
The Resource of Task Usage views and the calendar views are unable to produce the information that our Forman require.
I need more like an excel spreadsheet where Column A = Resources and Row 1 = Dates. Then the cells that align with the resource and the date will show the task for the day, similar to that of a times table situation.
Please help me change their old ways to a better MS Project way.
I have also tried this in a testdrive of P2007 but still can not get the task name to appear, i can only get the work hours to appear.