In the attached project, in the network diagram, the critical tasks are displayed in red as expected. I have used box styles to change the formatting of the nodes and created a new style called MyStandard.
When I change the duration of task C from 2w to 10w the critical path changes to go through C. However, the colour of the node remains blue. Similarly if I increase the duration of D to join the critical path e.g. to 22w it does not change red. However, the arrows always change to the correct colour.
I think I am misunderstanding "Format Box" which is overriding the "Box Styles" colours.
Could somebody advise me what I am doing wrong? Thanks.
When I change the duration of task C from 2w to 10w the critical path changes to go through C. However, the colour of the node remains blue. Similarly if I increase the duration of D to join the critical path e.g. to 22w it does not change red. However, the arrows always change to the correct colour.
I think I am misunderstanding "Format Box" which is overriding the "Box Styles" colours.
Could somebody advise me what I am doing wrong? Thanks.