Chart's Range vs. Report's Range

Status
Not open for further replies.

edteck

MIS
Feb 23, 2000
47
IE
I use CR7. I have a report which shows the number of work orders which have been raised in the period "Aged0to30Days". They are grouped by date.
Charting is on Change of "Date" vs. "Count of Work Orders".

At today's date the report shows work orders for various dates between 13/02/01 and up to and including 14/03/01. The charted information begins at 13/02/01 but ends at 08/03/01. What am I doing wrong?



 
Is this a "Group" or "Advanced" chart?
In your "change group expert" is the report grouped weekly? Ken Hamady
Crystal Reports Training/Consulting and a
Quick Reference Guide to VB/Crystal (including ADO)
 
Ken, the answer to your question :
In your "change group expert" is the report grouped weekly?
The answer is no.
[I had dismantled the report such that as it stands at the moment there is but one group "date".]
 
When you group by a date you get a "Break" setting that can be for each:
Day
Week
Month
etc.

I assume yours is DAY.

What are the settings on the data tab for the chart:
Group or Detail?
On Change of __?
Show __? Ken Hamady
Crystal Reports Training/Consulting and a
Quick Reference Guide to VB/Crystal (including ADO)
 
"Break" is set for DAY

The settings on the data tab for the chart:
Group
On Change of Date
Show Count of Work_Orders
 