Hi,
Working on a project that is being run on a 24hour basis, have set the working
time to 24hrs. The project is over a relatively small timescale so am describing
the tasks in hours.
My problem is; even though I am describing the tasks in hours the summaries
are showing in days, this would be OK only the days are 8 hour days whereas
I am working 24hrs. Clear? eg, I have 3 tasks, each of 8hr duration, but
the summary is showing 3 days, I am working 24hrs so this should only show
1day.
Either of two solutions would suit, change the summary duration to hours
or change the days to 24hr days.
Any help much appreciated.
GF
Working on a project that is being run on a 24hour basis, have set the working
time to 24hrs. The project is over a relatively small timescale so am describing
the tasks in hours.
My problem is; even though I am describing the tasks in hours the summaries
are showing in days, this would be OK only the days are 8 hour days whereas
I am working 24hrs. Clear? eg, I have 3 tasks, each of 8hr duration, but
the summary is showing 3 days, I am working 24hrs so this should only show
1day.
Either of two solutions would suit, change the summary duration to hours
or change the days to 24hr days.
Any help much appreciated.
GF