doctorswamp
Technical User
Hi
I'm stuck for ideas how to even start this. A job form stores start and end dates of various jobs, and the man hours needing to be provided during each job.
So Job xyz
- starts 1/3/07
- ends 15/6/07
- needs 30 man hours
If resource available is say 8 men doing 40 hours per week I'd like to be able to chart the total hours available per day, and the hours required per day for all jobs currently running. This would show at a glance any spare capacity or over commitment.
Eventually it would be good to divide the man hours into particular skills and do more complex planning, but first things first.
Any suggestions or pointers? FAQ didn't respond to capacity planning.
Many thanks
I'm stuck for ideas how to even start this. A job form stores start and end dates of various jobs, and the man hours needing to be provided during each job.
So Job xyz
- starts 1/3/07
- ends 15/6/07
- needs 30 man hours
If resource available is say 8 men doing 40 hours per week I'd like to be able to chart the total hours available per day, and the hours required per day for all jobs currently running. This would show at a glance any spare capacity or over commitment.
Eventually it would be good to divide the man hours into particular skills and do more complex planning, but first things first.
Any suggestions or pointers? FAQ didn't respond to capacity planning.
Many thanks