oufinny
Technical User
- Feb 14, 2008
- 3
I am trying to create a project that recognizes a contract requirement that is based on calendar days (one milestone is based on 14 calendar days, others are 42 and 84) versus what project does with the project calendar and a 5 day work week. I went in and remade the calendar, with an exception to recognize all days to have an 8 hour day but I cannot get tasks to add properly. For example, I did this and a task starting on 2/13 that should finish on 2/27 (14 calendar day duration) ends later.
At this point I am of the belief it is a conflict between the amount of working days in the month versus the project schedule that should recognize all 29/30/31 day months in 2008.
Any input on how I can make project understand a calendar that recognizes all days and adds them just like you are counting on a calendar would be greatly appreciated.
At this point I am of the belief it is a conflict between the amount of working days in the month versus the project schedule that should recognize all 29/30/31 day months in 2008.
Any input on how I can make project understand a calendar that recognizes all days and adds them just like you are counting on a calendar would be greatly appreciated.