When I change the Start and Finish dates of a task, the dates of the resources change automatically. Is there a way to change the Start and Finish dates of a Task without automatically changing the dates of individual resources? The reason I want to do this is as follows:
I may have a person that can only work on specific dates. However, I may want to Start the task earlier or end it later of which other people will be working on it. When I change the start and finish date of the task, I don't want the date of the resource to change.
Can I do that?
I may have a person that can only work on specific dates. However, I may want to Start the task earlier or end it later of which other people will be working on it. When I change the start and finish date of the task, I don't want the date of the resource to change.
Can I do that?