I have created a project schedule that had certain tasks starting on certain dates, i.e. Analysis A would start on 8/15/11. Since todays date is the 8/22/11 and the analysis hasn't started can i tell project to push any unstarted tasks to today's date until i input a completion percentage? Thank you.