Hi,
Project Plan re-cut question.
I need to work with an MS project plan as supplied by our programme office. It has a series of projects, and each of these has several things to deliver. Teams will carry tasks in each delivery. These are common across deliveries and projects.
For for example, a design task "Task 1" appears many times, e.g.:
Delivery A
----Task 1
---------Task 2
--------------Task 3
------------------Task 4
Delivery B
----Task 1
---------Task 2
--------------Task 3
------------------Task 4
Delivery C
----Task 1
---------Task 2
--------------Task 3
------------------Task 4
Also deliveries are staged (not shown). Task 1 is carried out by the same team in each case, and so on. What I would like to do is re-cut the plan so that it is useful for the teams as a task based schedule
Task 1 (Summary)
----Delivery A
-------------Delivery B
------------------------Delivery C
Task 2 (Summary)
--------Delivery A
-----------------Delivery B
----------------------------Delivery C
Task 3 (Summary)
--------Delivery A
-----------------Delivery B
----------------------------Delivery C
I could do this manually but there are 9000 lines on the project plans, with probably 100 design tasks that I have to deliver, over 1000 lines.
So if there is a way to cut the plan to show this, that would be great.
Project Plan re-cut question.
I need to work with an MS project plan as supplied by our programme office. It has a series of projects, and each of these has several things to deliver. Teams will carry tasks in each delivery. These are common across deliveries and projects.
For for example, a design task "Task 1" appears many times, e.g.:
Delivery A
----Task 1
---------Task 2
--------------Task 3
------------------Task 4
Delivery B
----Task 1
---------Task 2
--------------Task 3
------------------Task 4
Delivery C
----Task 1
---------Task 2
--------------Task 3
------------------Task 4
Also deliveries are staged (not shown). Task 1 is carried out by the same team in each case, and so on. What I would like to do is re-cut the plan so that it is useful for the teams as a task based schedule
Task 1 (Summary)
----Delivery A
-------------Delivery B
------------------------Delivery C
Task 2 (Summary)
--------Delivery A
-----------------Delivery B
----------------------------Delivery C
Task 3 (Summary)
--------Delivery A
-----------------Delivery B
----------------------------Delivery C
I could do this manually but there are 9000 lines on the project plans, with probably 100 design tasks that I have to deliver, over 1000 lines.
So if there is a way to cut the plan to show this, that would be great.