Calculating Correct Days

Status
Not open for further replies.

AntonioPerera

Vendor
Jan 29, 2006
91
AU
Hi,

My tasks look like this :

+Implementation 15.38 days
-Database creation 5 days
-Installation 1.38 days
-Payroll Implementation 3 days
-Other Implementation 2 days

The total calculated is based on the days range and that amounts to 15.38 days
However, I want it to calculate the actual days which is 5 + 1.38 + 3 + 2 = 11.38

How can I do that ?
 
It appears you are viewing Duration instead of Work. Insert the Work column.

Click on any column header to select the entire column
Press the Insert key
In the popup, select "Work" and click on OK
 
It looks like the "Work" column works well but shows everything in hours.
Is it possible to show the "Work" column details in Days instead of hours ?
 
Tools > Options > Schedule-tab and set "Work is entered in:" to "days
 