We have a remote site(G700 media gateway) connected to Hub site(s8720). We have a trunk-group in which we have 3 ds1 boards.
We need to replace one of 3 DS1 board at remote site.
My plan is to run these command at Hub site,
busy out board xxxxx(the board number to be replaced)
replace the ds1 board and
release board xxxxx
is that right approach or do i have to busy out trunk-group itself?
do i need to busy out at both hub and remote site?
We have a remote site(G700 media gateway) connected to Hub site(s8720). We have a trunk-group in which we have 3 ds1 boards.
We need to replace one of 3 DS1 board at remote site.
My plan is to run these command at Hub site,
busy out board xxxxx(the board number to be replaced)
replace the ds1 board and
release board xxxxx
is that right approach or do i have to busy out trunk-group itself?
do i need to busy out at both hub and remote site?