I am trying to calculate business hours between two date/time fields. I downloaded the Seagate UFL cruflwdays.dll - this allowed the std computation. It even had provision for holidays.
BUT - I have two sets of working hours in a week.
Mon-Fri are 09:00 - 18:00
Sat is 10:00 - 13:00
The only way I can get close to the answer is to do the calc twice. Once, assuming the working week is Mon-Fri and the second assuming the working week is Saturday only. I think my problems occur when a job starts and/or finishes on a Saturday.
Any advice on this gratefully accepted.
Thanks
George
BUT - I have two sets of working hours in a week.
Mon-Fri are 09:00 - 18:00
Sat is 10:00 - 13:00
The only way I can get close to the answer is to do the calc twice. Once, assuming the working week is Mon-Fri and the second assuming the working week is Saturday only. I think my problems occur when a job starts and/or finishes on a Saturday.
Any advice on this gratefully accepted.
Thanks
George