Hi,
I would like to know how I (and if possible) can set ms project to automatically change the dates of my tasks. Here's my example
I have two tasks :
Task 1: starts on Feb27 ends on March 2nd;
Task 2: starts on March 5th ends on March;
-Task 1 need to be completed before task 2 starts;
-I have set up a baseline on the entire project;
-Task are also set up to start as early as possible.
Let's pretend task 1 is completed by the end of the day on Feb27. So in the %completed column I enter 100%.
By saying task 1 is completed at 100% I would like to see the dates on task 2 to automatically change so it will start on Feb27 as well. This would probably mean that the end date on task 1 will move from March 2nd to Feb27.
Is this there a way to do this automatically in Ms Project ?
Thanks for your help
Regards
Ed
I would like to know how I (and if possible) can set ms project to automatically change the dates of my tasks. Here's my example
I have two tasks :
Task 1: starts on Feb27 ends on March 2nd;
Task 2: starts on March 5th ends on March;
-Task 1 need to be completed before task 2 starts;
-I have set up a baseline on the entire project;
-Task are also set up to start as early as possible.
Let's pretend task 1 is completed by the end of the day on Feb27. So in the %completed column I enter 100%.
By saying task 1 is completed at 100% I would like to see the dates on task 2 to automatically change so it will start on Feb27 as well. This would probably mean that the end date on task 1 will move from March 2nd to Feb27.
Is this there a way to do this automatically in Ms Project ?
Thanks for your help
Regards
Ed