This is probably a hopeless question...
Does anybody know if you can create a milestone that automatically updates to complete if its predeccors are completed?
I have a plan that is huge and I would dearly love a "self updating" milestone to save me monitoring 9 different tasks throughout a few thousand rows.
Is it possible (without coding)?
Thanks
tOOnaway
Does anybody know if you can create a milestone that automatically updates to complete if its predeccors are completed?
I have a plan that is huge and I would dearly love a "self updating" milestone to save me monitoring 9 different tasks throughout a few thousand rows.
Is it possible (without coding)?
Thanks
tOOnaway