Position: 1
Name: On-costing Applies
Description: Sets whether an on-cost will be added to costs incurred on the Work Order.
Values: Either Y or N
Position: 2-6
Name: On-cost Rate (format 999v99)
Description: Sets the rate at which on-costs will be applied
Values: 000.00
Position: 7-10
Name: Default Service Level Agreement
Description: Pre-defined SLA’s may be referenced here that will populate the appropriate fields on a Work Request
Values:
Position: 11-22
Name: Default Standard Estimate or District/Std Job
Description: Pre-defined Std Estimates or District defined Std Jobs can be referenced here. When saving the Work Request an Estimate or Work Order can be automatically created from the std entity referenced.
Values:
Position: 23
Name: Estimate/Standard Job Indicator (E/J)
Description: Mandatory if Default Standard Estimate or District/Std Job entered
Values: Either E or J
Position: 24
Name: Work Order Auto Create Flag
Description: This is a flag of either Y or N to indicate if the automatic creation of a referenced entity is required.
Values:
Position: 25
Name: Inst-I Remove-R Chgeover-C Scrap-S Salvage-V Mix-M
Description: Used for Utilities accounting
Values:
Position: 26
Name: Labour Profit (Enter Y) or Risk (Enter N) Factor
Description: This is to define the adjustment +/- to the labour for an estimate.
Values: Y applies the factor as an add on, N deducts the factor
Position: 27-31
Name: Labor Risk Factor (Format 999.99)
Description: This is the amount in % terms that the labour value is to be adjusted by.
Values: 000.00
Position: 32
Name: Equip Profit (Enter Y) or Risk (Enter N) Factor
Description: This is to define the adjustment +/- to the Equipment for an estimate.
Values: Y applies the factor as an add on, N deducts the factor
Position: 33-37
Name: Equip Risk Factor (Format 999.99)
Description: This is the amount in % terms that the Equipment value is to be adjusted by.
Values:
Position: 38
Name: Material Profit (Enter Y) or Risk (Enter N) Factor
Description: This is to define the adjustment +/- to the Material for an estimate
Values: Y applies the factor as an add on, N deducts the factor
Position: 39-43
Name: Material Risk Factor (Format 999.99)
Description: This is the amount in % terms that the Material value is to be adjusted by.
Values:
Position: 44
Name: Overall Profit (Enter Y) or Risk (Enter N) Factor
Description: This is to define the adjustment +/- to the Overall value for an estimate
Values: Y applies the factor as an add on, N deducts the factor
Position: 45-49
Name: Overall Risk Factor (Format 999.99)
Description: This is the amount in % terms that the Overall value is to be adjusted by.
Values:
MT table
Used in conjunction with 'Work Order Type' to further describe the type of work being performed. It designates the basic category of work or maintenance being performed. For example if the work order type is maintenance.
We do not use associated values with the MT table.
This site uses cookies to help personalise content, tailor your experience and to keep you logged in if you register.
By continuing to use this site, you are consenting to our use of cookies.